Hello
We have a project that is using an 8-relay GreenMAX panel with Sapphire and ODC0P-00W. Six of the relays(RELAY-1CB) are doing on/off daylight harvesting in an atrium area. The atrium is sometimes used for picture taking so the customer now wants an override switch to force the lights on...
If you had two 40amp loads could you measure both loads with one meter and one CT?
or do you need two CTs but one meter?
What does this refer to Could you have three loads measured by one meter?